UNIT-II Mill Expansion Plan – Implementation Summary
- The scope of the project covers, broadly:
– Installation of a 400 tpd Chemical Hardwood Pulp mill (VALMET)
– A Chemical Recovery Island (ANDRITZ) and
– A 20 MW Turbo Generator (BHEL)
– Other auxiliaries like Chipper, ClO2 plant, Water /Effluent treatment systems - Project Cost estimate : Rs.1250 Crore (Being revised to Rs.1330 Cr.)
- All Plant and machinery deliveries completed.
- Civil works completed in all areas.
- Equipment Erection have been completed in all the plants.
- Piping Erection works completed in all areas.
- Electrical and C&I completed in all areas.
- Pulp Mill is ready for receiving raw material and chemicals.
- Evaporator ready for receiving black liquor
- Recovery Boiler : Ready for commissioning with one pass of ESP.
- Due to incessant rains during Oct/Nov., progress of OSBL piping works including steam piping,
HT/LT cabling, insulation works etc., were impacted.